History
The Workstation Program was funded to address the IACC goal of achieving
universal access to computing and communications for faculty. The
IACC model for providing universal access involves two phases:
- Catch-up Phase--Phase I--to provide new PCs to those without
or those who have an obsolete system
- Sustenance Phase--all subsequent phases--to begin replacing
the PCs of about one-third of the faculty each year to achieve
the goal in which no full-time faculty member has a system more
than three years old.
Fiscal Year 96/97 (Phase I): 440 new faculty
workstations--229 Apples and 221 Dells--were installed during May/
June, 1997.
- Analysis: because of the large number of workstations
needing replacement, workstations were leased to maximize purchasing
power. This caused a number of problems:
- The goal of replacing one-third of all workstations each
year became difficult to achieve because of the disproportionate
number of workstations purchased this cycle.
- Leasing became a necessary model as debt rolled from Fiscal
Year to Fiscal Year, thus adding extra expense to the program.
- The large numbers of workstations installed at one time
required that installations be contracted out at additional
expense.
- Administration of department charge-backs, lease terms,
box storage, and buyouts became increasingly confusing and
time-consuming.
Fiscal Year 97/98 (Phase II): 187 new
faculty workstations--62 Apples and 125 Dells-- were installed during
February/ March, 1998.
- Analysis: leasing continued, but due to the cost of the
FY 96/97 lease and budget cuts, the number of workstations purchased
fell well below the one-third mark of 271. Installations continued
to be contracted out at additional expense.
Fiscal Year 98/99 (Phase IIIa & IIIb):
165 new faculty workstations--69 Apples and 96 Dells-- were installed
during August and October, 1998.
- Analysis: leasing continued and, due to the cost of the
previous lease cycles, even fewer workstations were purchased
and contracted out for installation.
Fiscal Year 99/00 (Phase IVa & IVb):
280 new faculty workstations--110 Apples and 170 Dells-- were installed
during August, 1999 and July, 2000.
- Analysis: Phase IVa workstations were leased, but Phase
IVb workstations were financed internally by Cal Poly, resulting
in significant cost-savings. This, in combination with aggressive
price negotiations with vendors, allowed the program to purchase
a larger number of workstations and exceed the 271 target.
Fiscal Year 00/01: 284 faculty and 4 support
workstations-- 103 Apples and 185 Dells-- were purchased and installed
between March and June, 2001.
- Analysis: for the first time all workstations were financed
internally, resulting in significant savings and reducing over-all
program debt. Workstation orders were processed quarterly with
installations performed by User Support Services taking place
continually. Changes to the program resulted in the following:
- Per workstation support costs (including financing, warranty,
and installation) fell from $1,000 to less than $500.
- The average cost per workstation/ peripherals rose from
$1,780 to $2,000, resulting in better workstations on the
desktop.
- Debt for the program fell from $766,000 to $633,000.
- More users opted for laptops to better utilize mobile teaching
technologies.
- The number of HelpDesk support calls fell to the lowest
level since inception of the program due to better qualified
technicians installing workstations.
Fiscal Year 01/02: 156 faculty
workstations, 66 ITS workstations, and 80 staff workstations were installed between July 01 and May 02.
- Analysis: faced with immediate budget cuts, a proposal
was presented to IACC, Logistical Coordinators, and others
to move to a four-year replacement cycle (for a target
total of 219 workstations per year). The allocation
was reduced to 156 workstations. In addition, the amount spent
per workstation was reduced from $2,000 to $1,610 with a goal of eliminating all
debt from the program.
Fiscal Year 02/03: 166 faculty
workstations were replaced.
- Analysis: faced with on-going budget cuts, the allocation
was 166 workstations. In addition, the amount spent
per workstation was reduced from $2,000 to $1,610 until all
debt is eliminated from the program. With these changes we saved $100,000 in FY 02/03 and eliminated all debt for
FY 03/04.
Fiscal Year 03/04: an estimated 219 faculty
workstations will be replaced.
- Analysis: the workstation allocation will equalize at
219 for a four-year cycle. In addition, the amount spent per workstation
will rise from $1,610 to $2,000. The budget can be reduced by
$190,000 and the program will have no debt.
|